Ref T11153. If you have a build plan like this:
- Lease machine A.
- Lease machine B.
- Run client-tests on machine A.
- Run server-tests on machine B.
...and we get machine A quickly, then finish the tests, we currently do not release machine A until the whole plan finishes.
In the best case, this wastes resources (something else could be using that machine for a while).
In a worse case, this wastes a lot of resources (if machine B is slow to acquire, or the server tests are much slower than the client tests, machine A will get tied up for a really long time).
In the absolute worst case, this might deadlock things.
Instead, release artifacts as soon as no waiting/running steps take them as inputs. In this case, we'd release machine A as soon as we finished running the client tests.
In the case where machines A and B are resources of the same type, this should prevent deadlocks. In all cases, this should improve build throughput at least somewhat.